Timeline updated March 2017.

July 2002 - 40m mast erected.
February 2005 - EPBC determination received.
June 2005 – Community open day/survey.
April 2008 - Planning approval obtained.
April 2011 - 80m tower erected.
November 2011 – Planning permit commencement extension.
March 2013 – Endorsed Development Plans approved.
October 2013 – Planning permit completion extension granted.
June 2015 – Planning permit completion extension granted.

August 2016 - Planning permit tip height amendment application lodged.
October 2016 - Public notification to be confirmed.

anuary 2017 - Planning Permit Amendment public notification concludes.

March 2017 - Planning Panels Victoria panel hearing held.

April 2017 - Planning Panels Victoria panel hearing recommendations expected.

Targeting tendering for round 1 and 2 of the VRET expected Q2 and or Q3 2017.