Timeline updated March 2017.

July 2002 - 40m mast erected.
February 2005 - EPBC determination received.
June 2005 – Community open day/survey.
April 2008 - Planning approval obtained.
April 2011 - 80m tower erected.
November 2011 – Planning permit commencement extension.
March 2013 – Endorsed Development Plans approved.
October 2013 – Planning permit completion extension granted.
June 2015 – Planning permit completion extension granted.

August 2016 - Planning permit tip height amendment application lodged.

October 2016 - Public notification to be confirmed.

January 2017 - Planning Permit Amendment public notification concludes.

March 2017 - Planning Panels Victoria panel hearing held.

April 2017 - Planning Panels Victoria panel hearing recommendations completed.

May 2018 - Planning Permit amendment approved.

September 2018 - Long term investor secured.

Q4 2018 - Announcement on off-take and construction expected.